Forum Home > Project Management Professional (PMP) > What is the difference between "Lag" & "Float" both appears to be the same?

s_anupkumar
Site Owner
Posts: 57

As per PMI, “Lag” is the waiting time between activities. “Float” is used to cover the delay between activities. Discussed in detail as part of critical path & network diagrams in project schedule management.

February 3, 2015 at 2:58 AM Flag Quote & Reply