Forum Home > Program Management Professional (PgMP) > What is the difference between "Phase-gate review" and "Other decision-point reviews" ?

s_anupkumar
Site Owner
Posts: 57

"Phase-gate reviews" happen based on "defined frequencies" (i.e. upon completion of a phase / starting a phase), check the strategic alignment, respond to a critical risk / issue, program compliance etc.

"Other decision-point reviews" happens based on "event based" whenever certain key decisions which are deemed appropriate to be taken. Such reviews happen in co-ordination with portfolio management, program sponsor etc. in-line with the strategic objectives. For example: Review to support of portfolio board to prepare the annual budget of the organization

February 3, 2015 at 3:30 AM Flag Quote & Reply