Forum Home > Program Management Professional (PgMP) > Program closure related tasks & the order of events:

s_anupkumar
Site Owner
Posts: 57

Tasks related to Program closure happens as follows:

To keep it simple: As part of program closure,

All components to be closed

- Procurment closure to be done (Some procurements may be specific to a individual component. Those procurements need to be closed by satisfying the necessary contractual terms & conditions)

- Administrative closure to be done

Then,

Program closure to follow

- Procurement closure (It's a recommended practice to centralize procurements in program level which can satisfy the component needs within the program. Such procurements which happens in program level to be closed by satisfying the necessary contractual terms & conditions)

- Admin closure (Final report, LL, resrouce disposition, update to organization assets etc). Most of these activities expected to happen in parallel. however, resource disposition to be consider to happen in the end because we need resources to be involved in certain tasks such as to perform final review, collect LL etc.

February 4, 2015 at 3:11 AM Flag Quote & Reply